Parliamentary questions can be asked by any MSP to the Scottish Government or the Scottish Parliamentary Corporate Body. The questions provide a means for 成人快手 to get factual and statistical information.

  • Written questions must be answered within 10 working days (20 working days during recess)
  • Other questions such as Topical, Portfolio, General and First Minister's Question Times are taken in the Chamber

Urgent Questions aren't included in the Question and Answers search.  There is a SPICe fact sheet listing Urgent and emergency questions.

Find out more about parliamentary questions

Filter your results Hide all filters

Dates of parliamentary sessions
  1. Session 1: 12 May 1999 to 31 March 2003
  2. Session 2: 7 May 2003 to 2 April 2007
  3. Session 3: 9 May 2007 to 22 March 2011
  4. Session 4: 11 May 2011 to 23 March 2016
  5. Session 5: 12 May 2016 to 5 May 2021
  6. Current session: 12 May 2021 to 29 April 2025
Answer status
Question type

Displaying 1070 questions Show Answers

|

Question reference: S6W-29172

  • Asked by: Oliver Mundell, MSP for Dumfriesshire, Scottish Conservative and Unionist Party
  • Date lodged: Tuesday, 20 August 2024
  • Current Status: Answered by Ivan McKee on 27 August 2024

To ask the Scottish Government, further to the answer to question S6W- 28736 by Ivan McKee on 7 August 2024, what consideration it has given to how the public and other stakeholders may perceive instances of planning permission being granted, and advance construction beginning, for associated grid infrastructure for wind farms that have yet to be determined by the Scottish Ministers.

Question reference: S6W-28951

  • Asked by: Oliver Mundell, MSP for Dumfriesshire, Scottish Conservative and Unionist Party
  • Date lodged: Tuesday, 06 August 2024
  • Current Status: Answered by Mairi Gougeon on 19 August 2024

To ask the Scottish Government whether an environmental impact assessment will be required to be carried out before any licence is granted for the trial being proposed to keep adult salmon broodstock for the aquaculture industry in a trout fish farm at the headwaters of the River Annan.

Question reference: S6W-28952

  • Asked by: Oliver Mundell, MSP for Dumfriesshire, Scottish Conservative and Unionist Party
  • Date lodged: Tuesday, 06 August 2024
  • Current Status: Answered by Jim Fairlie on 16 August 2024

To ask the Scottish Government what grant support (a) is currently available and (b) it plans to introduce for egg producers to upgrade their farms and to improve animal welfare.

Question reference: S6W-28736

  • Asked by: Oliver Mundell, MSP for Dumfriesshire, Scottish Conservative and Unionist Party
  • Date lodged: Thursday, 25 July 2024
  • Current Status: Answered by Ivan McKee on 7 August 2024

To ask the Scottish Government for what reason additional grid capacity and infrastructure at Bearholm substation has reportedly been granted planning permission, in light of the Rivox and Scoop Hill Windfarm planning applications reportedly having not yet been determined.

Question reference: S6W-28227

  • Asked by: Oliver Mundell, MSP for Dumfriesshire, Scottish Conservative and Unionist Party
  • Date lodged: Monday, 17 June 2024
  • Current Status: Answered by Tom Arthur on 15 July 2024

To ask the Scottish Government when Strengthening Communities Programme funding for the financial year 2024-25 will be released to the Development Trusts Association Scotland to allow local organisations to receive funds.

Question reference: S6W-28336

  • Asked by: Oliver Mundell, MSP for Dumfriesshire, Scottish Conservative and Unionist Party
  • Date lodged: Monday, 24 June 2024
  • Current Status: Answered by Gillian Martin on 9 July 2024

To ask the Scottish Government what action is being taken to address the reported sewage discharge in the Kirkconnel/Kelloholm area.

Question reference: S6W-27959

  • Asked by: Oliver Mundell, MSP for Dumfriesshire, Scottish Conservative and Unionist Party
  • Date lodged: Friday, 31 May 2024
  • Current Status: Answered by Jenni Minto on 14 June 2024

To ask the Scottish Government whether it has received a business case regarding the provision of diabetes technology, and, if so, when it plans to make a decision.

Question reference: S6W-27989

  • Asked by: Oliver Mundell, MSP for Dumfriesshire, Scottish Conservative and Unionist Party
  • Date lodged: Monday, 03 June 2024
  • Current Status: Answered by Jenni Minto on 14 June 2024

To ask the Scottish Government whether the new funding announced for diabetes technology will be ringfenced.

Question reference: S6W-28050

  • Asked by: Oliver Mundell, MSP for Dumfriesshire, Scottish Conservative and Unionist Party
  • Date lodged: Wednesday, 05 June 2024
  • Current Status: Answered by Neil Gray on 13 June 2024

To ask the Scottish Government what the average ambulance response time is for a cardiac arrest in NHS Dumfries and Galloway.

Question reference: S6W-27962

  • Asked by: Oliver Mundell, MSP for Dumfriesshire, Scottish Conservative and Unionist Party
  • Date lodged: Friday, 31 May 2024
  • Current Status: Answered by Angela Constance on 10 June 2024

To ask the Scottish Government what steps it is taking to review cyber security, in light of the reported recent breaches at Scottish public bodies.